Production → Briefing is the screen that says what to worry about before anybody asks. It opens with a few sentences — how many units are due today (and on which orders) against capacity, how many orders cannot move, how many orders and units are past the date we promised, how many will miss on the current plan, and which days in the next fortnight are booked over capacity.
Under that, every open order that needs attention, worst first, in four buckets:
- Blocked — something must change before it can move at all — an unpaid deposit, a credit hold, material short with nothing on order (only where the workspace has said material shortages block)
- Late — the date we promised has passed and it is not finished
- At risk — on the current plan it will miss — glass landing after the promise, work scheduled past it, a truck going too late
- Watch — worth a look, not yet a problem
Open any row for the reasons in plain sentences, each with what to do about it, plus the earliest date the job could realistically be ready.
The date it grades against. An order is late against the date WE PROMISED, never the date the customer asked for. Those are different facts: a dealer asking for next Friday on a six-week lead time is not a late order, it is a date nobody agreed to. An order with no promise is reported as UNPROMISED — not on time and not late — because nothing can grade it until somebody commits to a date.
The weather at the top. The screen, the emailed brief and the printed sheet all open with what it is doing outside — a crew loading trucks at 14°F is planning a different morning. It appears once somebody has named the town the plant is in, under Settings → Company identity → Plant location; until then there is simply no weather line. It is a live reading from a weather service, not something this system recorded.
This is the same help that ships inside Extrusia, where Josie, the built-in assistant, answers questions from these articles. All help articles.